 09/30/07 - Pouring the
foundations.
|
 10/08/07 - Site work
continues.
|
|
 12/12/07 -
Erecting a concrete shearwall.
|
 01/10/08 - Steel
Infrastructure begins to take shape on the ICU and Central Sterile
Department.
|
|
 02/03/08 - Aerial photo
with existing Physician Office Building (POB), the main elevator bank and
the steel structure for the Emergency Dept., Central Energy Plant (CEP)
and the loading dock.
|
 02/15/08 - Aerial photo
progress of the project to date. |
|
 02/15/08 - Setting the inside formwork on the
staircase adjacent to the Lab.
|
 02/15/08 -
Pouring the slab for the north end of Surgery (2nd Fl).
|
|
 03/03/08 - Starting the
steel erection for Administration (1st Fl), Pharmacy and Lab (2nd Fl) and
one of two Medical/Surgical Units (3rd Fl).
|
 03/03/08 - Aerial photo
includes new steel structure for the dining area and discharge (1st Fl),
Surgical Recovery (2nd Fl) and one of two Medical/Surgical Units (3rd
Fl).
|
|
 03/05/08 - Pouring the
roof slab over the Mother/Baby Unit (3rd Fl).
|
 03/14/08 - Aerial photo
includes new steel structure for Administration (1st Fl), Pharmacy and Lab
(2nd Fl) and one of two Medical/Surgical Units (3rd
Fl).
|
|
 03/21/08 - Placing wall
studs in the Surgery Area (2nd Fl).
|
 04/01/08 - Aerial photo
with steel structure being erected for ED & Imaging (1st Fl), Labor
& Delivery, Endoscopy (2nd Fl) and ICU (3rd
Fl).
|
|
 04/14/08 - Building
steel is 95% complete and the parking lot paving has
started.
|
|
|
 04/28/08 - Commemorative shirts for the
Topping Out Ceremony.
|
 04/28/08
- A "Top Hat" placed on the side of the building signified the
event.
|
|
 04/28/08 - Lunch was
enjoyed by everyone at the Topping Out Ceremony.
|
 05/14/08 Aerial photo of the main entrance. The
future main entry boulevard will feature a fountain pool and a glass
covered portico.
|